- 1 March 2023
- Posted by: Brendan Sharkey
- Categories: Commercial Property, Construction Law, Property, Residential Property
No Comments
Stamp Duty –
Residential Development Refund Scheme for non-residential land
BACKGROUND
- Section 83D of the Stamp Duties Consolidation Act 1999 provides for a refund to both single dwelling units and multi-unit developments
- The date construction works commence has been extended from 31 December 2022 to 31 December 2025
SINGLE DWELLING UNITS
Conditions to meet
- Land only is transferred
- A stamp duty return is filed and duty paid at the rate of 7.5%
- Limit on area of land to qualify for a refund – dwelling and curtilage up to 0.4047 hectares
- Construction work must commence on the land within a period of 30 months running from the date of transfer of the land
- Construction work must be completed within 30 months of a local authority confirming a commencement notice as valid
Claiming refund
- A refund can be claimed once construction work commences
- A time limit of 4 years arises to make a claim, running from the date a local authority acknowledges a commencement notice as valid
- The refund is the difference between the 7.5% duty and the old rate of 2%, which is eleven fifteenths of the 7.5% rate
Clawback
- A refund may be clawed back if construction work is not completed within 30 months of a local authority acknowledging receipt of a commencement notice
MULTI-UNIT DEVELOPMENTS
Conditions to meet
- Land only is transferred
- A stamp duty return is filed and duty paid at the rate of 7.5%
- 75% test:-
(a) No less than 75% of the total surface area of the land must be occupied by dwelling units or
(b) The gross floor space of the dwelling units must account for at least 75% of the total surface area of the land - A commencement notice is served at each phase of a development and where the 75% test is met a refund can be claimed. If however a particular phase does not meet the 75% test but where the 75% test will be satisfied for an entire development, then a developer can opt to defer the claim until construction works commence on the final phase of a development. A refund can however always be sought for earlier phases where such phases satisfy the 75% test
- Construction work must commence on the land within a period of 30 months running from the date of transfer of the land
- For a phased development each phase must be completed within 30 months of a local authority confirming a commencement notice as valid
- The date of completion of a phase is the date a Certificate of Compliance on Completion is registered by a local authority
Claiming refund
- A refund can be claimed once construction work commences, and should not be made until the 75% test is satisfied
- A time limit of 4 years arises to make a claim, running from the date a local authority acknowledges a commencement notice as valid
- The refund is the difference between the 7.5% duty and the old rate of 2%, which is eleven fifteenths of the 7.5% rate
Clawback
- A refund may be clawed back if construction work is not completed within 30 months of a local authority confirming a commencement notice as valid (for each phase), or
- where the 75% test is not satisfied when construction works are completed
Analysis
- Extension of the date to commence works from 31 December 2022 to 31 December 2025 is welcome
- The 75% test to claim a refund may be viewed as too rigid for developments that comprise largely houses, as roads, green areas and footpaths often make up more than 25% of the land.
For further information on this topic, please contact Brendan Sharkey on bsharkey@reddycharlton.ie